Monday, April 28, 2014

Tentative Renovation Timeline

Finish up plumbing Monday. I can hear them cleaning and packing up now!
Tuesday- finish electrical, install exhaust fans, move window.
Wednesday- Plumbing/electrical inspection. If inspection passes, dry waller out Wednesday afternoon or Thursday for day 1 of 2. Put in floor of bathroom.
Thursday- Day 1 or day 2 of dry wall and mud. Stucco repair on window?
Friday- Finish dry wall and mud or install cabinets.
Monday- Install cabinets.
Tuesday- Paint kitchen/bath/laundry closet.
Wednesday/Thursday- Don does tile and flooring.
Thursday- Finish flooring and install appliances.
Friday/Saturday/Sunday- DINNER PARTIES!!

Let's see how close we  can get to this. My money is on the inspections throwing wrenches all over the place. Fingers crossed...